home *** CD-ROM | disk | FTP | other *** search
/ Cream of the Crop 1 / Cream of the Crop 1.iso / BUSINESS / SKED_433.ARJ / SCHEDULE.DOC < prev    next >
Text File  |  1992-07-09  |  107KB  |  1,541 lines

  1.                                     
  2.                                SCHEDULE
  3.                          Version 4.00/4.10/4.33
  4.                                   by
  5.                            William H. Logan
  6.  
  7. SCHEDULE 4.33 Adds BOLD print for the task numbers and task date lines
  8. as well as the task comment and ending date. In addition, some other
  9. minor bugs have been fixed. I also added the feature that if you press
  10. <ENTER> while editing, entering actual dates, or entering status
  11. comments, you will be returned to the Main Menu.
  12.  
  13. Version 4.5 will steal the Top Line Menu Bar approach so widely used in
  14. programs these days. It is not and will not be a Windows Version,
  15. however, it should run well in a Windows DOS window. It really likes
  16. DR-DOS 6.00, but then so do I and almost everyone else who has used
  17. DR_DOS 6.00.
  18.  
  19. While CLIPPER does not support MOUSE use, I can probably tell a user how
  20. to get the MOUSE to work if you have a LOGITECH with Ver 6.00 of their
  21. drivers. Almost anything can be moused with the new drivers!
  22.  
  23. If any users desire a special version, or some minor enhancements or
  24. changes, I will be happy to prepare and deliver such a version.
  25.  
  26. SCHEDULE Version 4.1 fixes some minor problems in Ver 4.00. The User
  27. Documentation, such as it is, is un-changed.
  28.  
  29. SCHEDULE Version 4.00 represents significant fixes and alterations from
  30. previous version(s).  It is still 'shareware' and if you use and like
  31. it, you are expected to make some contribution to the author for his
  32. efforts.
  33.  
  34. Notes:
  35. 1: Your old version schedules may be converted to the new format via
  36. SKEDCONV. That's all it does and it won't hurt an already converted
  37. schedule database.
  38.  
  39. 2: This file has some special characters as borders and uses some
  40. lines longer than 80 characters.  In order to see it all, you should be
  41. looking at it via the LIST.COM program.  Selections from the Main Menu
  42. are set out as <A> or <B>.  List will happily go and find that for you.
  43.  
  44. 3: THIS PROGRAM REQUIRES A WIDE CARRIAGE PRINTER.  BE SURE YOU HAVE IT
  45. ON AND 'ON-LINE' WITH WIDE PAPER LOADED!!
  46.  
  47. 4: If you use any of the included "test" files, first load them up, that
  48. is, select the proper database and then use the <LIST> feature to see the
  49. dates. If the dates are way off and they probably will be, then use
  50. <DATE TRICKS> to slide them all ahead to a more reasonable date. Some of
  51. the test files are quite old now and you may need to do this to get them
  52. to print properly. I suggest you slide all the dates, that is, both
  53. planned and actual.
  54.  
  55. 5: If you enter an actual date and no actual stop date, then you will
  56. have the chart precessed for you automatically. See Section D, below.
  57.  
  58.  
  59. Disclaimer: This program/system has been in use for over 6 years in one
  60. form or another and has been extensively tested, however, you may do
  61. things that may lead you to incorrect conclusions.  The author accepts
  62. no responsibility whatsoever for any loss of revenue, jobs or any other
  63. bad actions that may occur as a result of the use of this program.
  64. Before you make any decisions based on results you are advised to play
  65. and test extensively on the test files provided or on test files of your
  66. own making. I will attempt to clarify the actions of the program for
  67. those who register the program.  Any bugs or modification suggestions
  68. are gratefully acknowledged and will be corrected ASAP.
  69.  
  70. This system is a Project Planner/Estimator and Gannt Chart Scheduling
  71. program that has been in use and development for about 7 years.  It began
  72. in M-BASIC on an old Kaypro 2 and has now gone through dBASE 2.1 2.43,
  73. III+, and finally to Clipper.  It is released into the public domain as
  74. shareware, which means if you use it and it is helpful to you, then a
  75. contribution to the author is expected.  Contributions are accepted in
  76. any amount, but $50 is suggested, as this program is EXTREMELY POWERFUL
  77. and very flexible.  Please feel free to distribute the program to your
  78. friends and associates.  If you do, only give them SKED_433.ZIP, that way
  79. they will get all of the stuff they need.
  80.  
  81. Significant changes in Ver 4.00:
  82.     1. Select database one time.
  83.     2. Places for 8 personnel per task.
  84.     3. Corrected 'un-friendly' things in use of databases i.e., you
  85.     can't use SKED, the shell database.
  86.     4. Added linked tasks. See explanation below.
  87.     5. Set default parameters in the 'tricks' programs to 1.00 vice 0.00.
  88.     6. Allow tricks to all tasks or only one task.
  89.     7. Added sub tasks.
  90.     8. Shortened index time.
  91.     9. Added actual time to screen list.
  92.  
  93.  
  94. No apologies for the documentation.  I write code.  Not books.
  95.  
  96. Schedules are in DATABASES that are indexed (by CLIPPER).  Some data is
  97. kept in memory files and there is one format file.  I suggest you
  98. install the whole thing in a SKED or SCHEDULE directory and work from
  99. there.  In database names we capture the 8th character (or the last one)
  100. so you get to use ONLY 7 characters for your names.
  101.  
  102. There are some test files to play with called TEST_1.DBF and TEST_2.DBF,
  103. Don't worry about index and memory files as they will be created when they
  104. are needed.  Note that by the time you get these test files they may
  105. have been added to or taken from so don't be too upset if yours doesn't
  106. look exactly like the examples shown here. Before you try to print the
  107. test schedules, you should look at them through the Main Menu <L>
  108. option. If the dates are way out of whack (and they may be), then do
  109. some DATE TRICKS <T> on them, sliding them forward enough to get them
  110. into a reasonable relationship to the current date.
  111.  
  112. Since the Schedule system is date based, it has a SETUP sub-routine that
  113. will be run before anything that might display or print garbled results
  114. is run.  It can be skipped, but do so only if you KNOW the index files
  115. are up to date.
  116.  
  117. Version 4.00 introduces the concept of selecting a database before you
  118. do anything.  That is selection <S>.  If you wish to create a new
  119. schedule, that is selection <K>.  If you have not selected a database,
  120. then you can only do choices <U>, <K>, and <S>.  The database in use is
  121. shown below selection <S>.  If no name is here, you have not selected.
  122. Choice <U> is the system utilities that will allow you to do some stuff
  123. from inside SCHEDULE.  The most important of these is the setup of a
  124. printer re-direct. What this means is that your output that would
  125. normally go to a printer will go to a file called JUNK.XXX.  You can
  126. keep the file by renaming it if you wish.  It is convenient if you are
  127. working up a plan and don't want to print.  Everything normally sent to
  128. the printer is sent into the re-direct. The public domain program
  129. REPRINT is another excellent way to do re-directs.  Details of the
  130. utilities will be explained when we get there.
  131.  
  132. SCHEDULE considers man-hours (or woman-hours) as a Direct Cost.  Each
  133. task line in the schedule can have 8 personnel assigned for differing
  134. amounts of time and at different hourly rates.  All man-hour costs are
  135. accumulated and displayed on the printed schedule.  Other Direct Costs
  136. are:
  137.  
  138.            Travel
  139.            Food
  140.            Lodging
  141.            Auto
  142.            Equipment
  143.            Copies
  144.            Admin
  145.            Support
  146.            Miscellaneous
  147.  
  148. There surely are more categories for ODCs than this, but these have been
  149. adequate for all our work.  At the end of the printed schedule a Project
  150. Summary is printed.  An example of that summary is:
  151.  
  152.           PROJECT LENGTH IS   214 DAY(s)
  153.  
  154.           EACH SYMBOL REPRESENTS  2 DAY(s)
  155.  
  156.           TOTAL  ESTIMATED MAN-HOURS          =====>          2385 M/H
  157.  
  158.           TOTAL ESTIMATED MAN-HOUR COSTS      =====> $   115364.71
  159.  
  160.           TOTAL PROJECTED OTHER DIRECT COSTS  =====> $    19159.36
  161.  
  162.           TOTAL PROJECTED COST                =====> $   134524.07
  163.  
  164. This tells you what it will cost totally, what the ODCs are, how many
  165. man- hours are needed and how many days, start to finish, it will take.
  166. All you put in was the individual task values and dates.  In addition,
  167. there is a ODC report <G> that breaks down ODCs into the above
  168. categories and totals so that you can see how much you are planning for
  169. each one.  Actual costs are not included, though if some one were to
  170. ask ....
  171.  
  172.  
  173.  
  174. The Main Menu is arrived at by entering:
  175.  
  176.     C:\SKED>schedule
  177.  
  178. ╔══════════════════════════════════════════════════════════════════════════════╗
  179. ║ July 92                      GANTT CHART SCHEDULER               Ver 4.33    ║
  180. ║                                by William H. Logan                           ║
  181. ╚══════════════════════════════════════════════════════════════════════════════╝
  182. ╔═══════════════════════════════════════╗╔═════════════════════════════════════╗
  183. ║ A   -- Add tasks to a NEW or          ║║  I   -- Inflate/deflate M/H         ║
  184. ║        EXISTING Schedule (DATE TYPE)  ║║  T   -- Date Tricks                 ║
  185. ║ Z   -- Add tasks, NEW or OLD          ║║  R   -- Hourly Rate Tricks          ║
  186. ║        (LINK TYPE)                    ║║  Q   -- ODC Rate Tricks             ║
  187. ║ B   -- EDIT an Existing Schedule      ║║                                     ║
  188. ║                                       ║║  F   -- DELETE a Task in a Project  ║
  189. ║ C   -- PRINT a Schedule               ║║                                     ║
  190. ║ G   -- PRINT Direct Cost Breakdown    ║║  L   -- List Schedule to Screen     ║
  191. ║        Report                         ║║                                     ║
  192. ║                                       ║║  U   -- System Utilities            ║
  193. ║ D   -- Enter Actual Dates             ║║  K   -- Create New Schedule         ║
  194. ║ E   -- Enter Status Comments          ║║  S   -- Select Schedule             ║
  195. ║                                       ║║                                     ║
  196. ║ *   -- Quit to Operating System       ║║  Schedule ==>                       ║
  197. ╚═══════════════════════════════════════╝╚═════════════════════════════════════╝
  198. ╔══════════════════════════════════════════════════════════════════════════════╗
  199. ║         Enter your choice --->                                               ║
  200. ╚══════════════════════════════════════════════════════════════════════════════╝
  201.  
  202.     The first action will be to select a schedule, <S>
  203.  
  204. --------------------------------------------------------------------------------
  205. Database Files    # Records    Last Update     Size                             
  206. TEST_2.DBF               15    03/23/89       10036                             
  207. CM.DBF                   32    03/23/89       19522                             
  208. SKED.DBF                  0    03/23/89        1666                             
  209. TEST_1.DBF               13    03/23/89        8920
  210.  
  211.  
  212.  
  213.  
  214.           Enter The schedule name from the above list ---->                     
  215. --------------------------------------------------------------------------------
  216.  
  217. Note below, in the next screen that the name of the selected schedule is
  218. shown at the "Schedule ==> TEST_2" line, immediately below the "S"
  219. selection.
  220.  
  221. ╔══════════════════════════════════════════════════════════════════════════════╗
  222. ║ July 92                      GANTT CHART SCHEDULER               Ver4.33     ║
  223. ║                                by William H. Logan                           ║
  224. ╚══════════════════════════════════════════════════════════════════════════════╝
  225. ╔═══════════════════════════════════════╗╔═════════════════════════════════════╗
  226. ║ A   -- Add tasks to a NEW or          ║║  I   -- Inflate/deflate M/H         ║
  227. ║        EXISTING Schedule (DATE TYPE)  ║║  T   -- Date Tricks                 ║
  228. ║ Z   -- Add tasks, NEW or OLD          ║║  R   -- Hourly Rate Tricks          ║
  229. ║        (LINK TYPE)                    ║║  Q   -- ODC Rate Tricks             ║
  230. ║ B   -- EDIT an Existing Schedule      ║║                                     ║
  231. ║                                       ║║  F   -- DELETE a Task in a Project  ║
  232. ║ C   -- PRINT a Schedule               ║║                                     ║
  233. ║ G   -- PRINT Direct Cost Breakdown    ║║  L   -- List Schedule to Screen     ║
  234. ║        Report                         ║║                                     ║
  235. ║                                       ║║  U   -- System Utilities            ║
  236. ║ D   -- Enter Actual Dates             ║║  K   -- Create New Schedule         ║
  237. ║ E   -- Enter Status Comments          ║║  S   -- Select Schedule             ║
  238. ║                                       ║║                                     ║
  239. ║ *   -- Quit to Operating System       ║║  Schedule ==>  TEST_2               ║
  240. ╚═══════════════════════════════════════╝╚═════════════════════════════════════╝
  241. ╔══════════════════════════════════════════════════════════════════════════════╗
  242. ║         Enter your choice --->                                               ║
  243. ╚══════════════════════════════════════════════════════════════════════════════╝
  244.  
  245. A. Add Tasks - DATE TYPE
  246.  
  247. Beginning at the first choice, <A>, to add a task, the addition screen
  248. appears as below.  Note that in this type of record you must know the
  249. start and stop dates.  Both may be left blank, but if one is entered, so
  250. must the other.  The program will adjust records with a start date and
  251. no stop date or a stop date with no start date.  Date type tasks appear
  252. on the printed schedule as "*" lines.
  253.  
  254.  ╔═════════════════════════════════════════════════════════════════════════════╗
  255.  ║        03/23/89            Record Number ===>    16                         ║
  256.  ║        Gantt Chart Scheduler         Data Input                             ║
  257.  ║                                                                             ║
  258.  ║   Task Description -->   NEW TASK                                           ║
  259.  ║   Task Number      -->   1.11        Sub Task         -->   005             ║
  260.  ║                                                                             ║
  261.  ║   Start Date       -->   08/12/89                                           ║
  262.  ║   Stop Date        -->   09/14/89                                           ║
  263.  ║                                                                             ║
  264.  ║   PERSON                      26           56.00                            ║
  265.  ║                                0            0.00                            ║
  266.  ║                                0            0.00                            ║
  267.  ║                                0            0.00                            ║
  268.  ║                                0            0.00                            ║
  269.  ║                                0            0.00                            ║
  270.  ║                                0            0.00                            ║
  271.  ║                                0            0.00                            ║
  272.  ║   Other Direct Costs --->       0.00                                        ║
  273.  ║   Do you want to enter Direct Costs (Y/N)   --->                            ║
  274.  ║                  LEAVE PROPOSED START BLANK FOR UN-SCHEDULED ITEMS          ║
  275.  ║                                                                             ║
  276.  ╚═════════════════════════════════════════════════════════════════════════════╝
  277.  
  278.     When you wish to add other direct costs, enter <Y> to the Direct Costs
  279. questions. The next screen looks like:
  280.  
  281. --------------------------------------------------------------------------------
  282.                       Direct Cost Breakdown Editor                              
  283.                                                                                 
  284. Record Number ===> [   16]      Task Number ===> [1.11    ]   Sub ===> [005]    
  285. Task Description ====> [NEW TASK                                           ]    
  286. Name(s)          ====> [                                                   ]    
  287.                                                                                 
  288. Burden Rate          ====>   [1.39]                                             
  289.            Travel                         ====> [  2300.00]                     
  290.            Food                           ====> [   677.00]                     
  291.            Lodging                        ====> [   997.00]                     
  292.            Auto                           ====> [   285.00]                     
  293.            Equipment                      ====> [    46.00]                     
  294.            Copies                         ====> [    25.00]                     
  295.            Admin                          ====> [    18.00]                     
  296.            Support                        ====> [   150.00]                     
  297.            Miscellaneous                  ====> [   200.00]                     
  298.                                                                                 
  299.         Total Estimated Direct Cost       ====> [  4698.00]                     
  300.                                                                                 
  301. Notes                                                                           
  302.  [Brief notes on the various expenses that need clarification                ]
  303. --------------------------------------------------------------------------------
  304.  
  305.     When you have added the necessary data and any one of the account
  306. types may be left blank, then you may continue to add records.
  307.  
  308.  
  309.  ╔═════════════════════════════════════════════════════════════════════════════╗
  310.  ║                                                                             ║
  311.  ║                                                                             ║
  312.  ║                                                                             ║
  313.  ║        Add another record? (Y/N) ====>                                      ║
  314.  ║                                                                             ║
  315.  ║                                                                             ║
  316.  ║                                                                             ║
  317.  ╚═════════════════════════════════════════════════════════════════════════════╝
  318.  
  319. Z. Add Tasks - LINK TYPE
  320.  
  321.     This type of task requires a task number, a sub task number to begin
  322. with, and an initial start date. Linked tasks appear on the printed
  323. schedule as "#" lines.
  324.  
  325.  ╔═════════════════════════════════════════════════════════════════════════════╗
  326.  ║                                                                             ║
  327.  ║   Enter the TASK Number                -->   2.11                           ║
  328.  ║                                                                             ║
  329.  ║   Enter the Sub Task No. to begin with -->   5                              ║
  330.  ║                                                                             ║
  331.  ║                                                                             ║
  332.  ║                                                                             ║
  333.  ║                                                                             ║
  334.  ║                                                                             ║
  335.  ║                                                                             ║
  336.  ║                                                                             ║
  337.  ║                                                                             ║
  338.  ║                                                                             ║
  339.  ║                                                                             ║
  340.  ╚═════════════════════════════════════════════════════════════════════════════╝
  341.  
  342. Next, you will enter the start date and the number of days.  The value
  343. "offset" is how many days to adjust the start date of the next task
  344. relative to the ending date of the current task.  The program will
  345. calculate the stop date and set up the start date for the next task.
  346. This offset allows you to "stack" tasks by giving each the offset equal
  347. to its own length.  The result may be seen in the schedule example for
  348. Task 2.11.005 and on.
  349.  
  350.  
  351.  ╔═════════════════════════════════════════════════════════════════════════════╗
  352.  ║        03/23/89            Record Number ===>    17                         ║
  353.  ║        Gantt Chart ScheduleLinked Tasks - Data Input                        ║
  354.  ║                                                                             ║
  355.  ║   Task Description -->   NEW TASK                                           ║
  356.  ║   Task Number      -->  2.11         Sub Task         -->  005              ║
  357.  ║                                                                             ║
  358.  ║   Start Date       -->  06/13/89     Enter Length          -->           22 ║
  359.  ║                                      Offset for next task  -->   -22        ║
  360.  ║   Stop Date        -->  07/05/89                                            ║
  361.  ║                                                                             ║
  362.  ║    _______________             0            0.00                            ║
  363.  ║    _______________             0            0.00                            ║
  364.  ║    _______________             0            0.00                            ║
  365.  ║    _______________             0            0.00                            ║
  366.  ║    _______________             0            0.00                            ║
  367.  ║    _______________             0            0.00                            ║
  368.  ║    _______________             0            0.00                            ║
  369.  ║    _______________             0            0.00                            ║
  370.  ║   Other Direct Costs   --->     0.00                                        ║
  371.  ║   Do you want to enter Direct Costs (Y/N)   ---> _                          ║
  372.  ║                                                                             ║
  373.  ╚═════════════════════════════════════════════════════════════════════════════╝
  374.  
  375. The lined section is where you may enter the names, number of hours
  376. assigned and the hourly rates of up to 8 staff personnel.  Skipping to
  377. the next task, however, please note that the start date for the next
  378. task is also 06/13/89. Personnel may be entered for each task line in
  379. the schedule.  They are left out of the next example screen.
  380.  
  381.  ╔═════════════════════════════════════════════════════════════════════════════╗
  382.  ║        03/23/89            Record Number ===>    18                         ║
  383.  ║        Gantt Chart ScheduleLinked Tasks - Data Input                        ║
  384.  ║                                                                             ║
  385.  ║   Task Description -->   ANOTHER                                            ║
  386.  ║   Task Number      -->  2.11         Sub Task         -->  006              ║
  387.  ║                                                                             ║
  388.  ║   Start Date       -->  06/13/89     Enter Length          -->           34 ║
  389.  ║                                      Offset for next task  -->            0 ║
  390.  ║                                                                             ║
  391.  ║                                                                             ║
  392.  ║                                                                             ║
  393.  ╚═════════════════════════════════════════════════════════════════════════════╝
  394.  
  395.     At the conclusion of each task you are asked if you wish to add
  396. another task.
  397.  
  398. B. Edit
  399.  
  400. Schedule changes are edited on a line by line basis.  Each task line has
  401. a control number, the actual record number in the database, and this
  402. number is used to access records for edits.  All fields may be edited.
  403. Note that, if you are working on a 'linked' task, editing may disturb
  404. the linkage. Record numbers can be printed (or not) on the printed
  405. result or may be seen through selection <L>, screen list of schedule.
  406.  
  407. The first screen you see asks for the control number.  Note that it
  408. tells you how many records there are.  It will not allow you to try to
  409. edit more than you have.
  410.                                                                                 
  411. -------------------------------------------------------------------------------
  412.           Enter the control number to edit ---->   6                            
  413.                                                                                 
  414.           Enter <*> to end edit & go back to Main Menu                          
  415.                                                                                 
  416.                                                                                 
  417.                                                                                 
  418.                                                                                 
  419.                                                                                 
  420.           There are   18 records in the database                                
  421. -------------------------------------------------------------------------------
  422.  
  423.     Next, the EDIT screen looks like:
  424.  
  425.  
  426. -------------------------------------------------------------------------------
  427.           03/23/89            Record Number ===>     6                          
  428.                             Gantt Chart Scheduler                               
  429.                                  Data Input                                     
  430.                                                                                 
  431.      Task Description -->   FIRST                                               
  432.      Task Number      -->   5.11        Sub Task         -->   001              
  433.                                                                                 
  434.      Start Date       -->   07/01/89                                            
  435.      Stop Date        -->   07/13/89
  436.                                                                                 
  437.      NAME                        22           33.00                             
  438.                                   0            0.00                             
  439.                                   0            0.00                             
  440.                                   0            0.00                             
  441.                                   0            0.00                             
  442.                                   0            0.00                             
  443.                                   0            0.00                             
  444.                                   0            0.00                             
  445.      Other Direct Costs --->       0.00                                         
  446.      Do you want to enter Direct Costs (Y/N)   --->                             
  447.      LEAVE PROPOSED START BLANK FOR UN-SCHEDULED ITEMS                          
  448.                                                                                 
  449. -------------------------------------------------------------------------------
  450.  
  451.     If you wish, Other Direct Costs may be edited, by <Y> in the Direct
  452. costs place.
  453.  
  454.  
  455. C. Print Schedule
  456.  
  457. Schedules are printed from this selection.  The first action is to check
  458. and see if the setup routines need to be run.  If you have added any
  459. tasks, edited and dates, or done any date or expansion tricks, then you
  460. should run the setup.  I suggest you print one of the test schedules as
  461. many ways as you can to see the difference.
  462.  
  463.  ╔═════════════════════════════════════════════════════════════════════════════╗
  464.  ║                                                                             ║
  465.  ║        If you know that the setup procedures are correct, you may           ║
  466.  ║        skip the SETUP program                                               ║
  467.  ║        S will skip SETUP procedures -- or --                                ║
  468.  ║        D or <CR> will execute SETUP ---->                                   ║
  469.  ║                                                                             ║
  470.  ║                                                                             ║
  471.  ╚═════════════════════════════════════════════════════════════════════════════╝
  472.  
  473.     Assuming you do run SETUP, the screen looks like:
  474.  
  475.  
  476.  ╔═════════════════════════════════════════════════════════════════════════════╗
  477.  ║                                                                             ║
  478.  ║        Working on record number ---->    7  <----                           ║
  479.  ║                                                                             ║
  480.  ║                                                                             ║
  481.  ║                                                                             ║
  482.  ║                                                                             ║
  483.  ║                                                                             ║
  484.  ║                                                                             ║
  485.  ║                                                                             ║
  486.  ║                                                                             ║
  487.  ║                                                                             ║
  488.  ║                                                                             ║
  489.  ║                                                                             ║
  490.  ║                                                                             ║
  491.  ╚═════════════════════════════════════════════════════════════════════════════╝
  492.  
  493.     Then like:
  494.  
  495.  
  496.  ╔═════════════════════════════════════════════════════════════════════════════╗
  497.  ║                                                                             ║
  498.  ║        Working on record number ---->   18  <----                           ║
  499.  ║                                                                             ║
  500.  ║                                                                             ║
  501.  ║                                                                             ║
  502.  ║                                                                             ║
  503.  ║        Preparing the Task/Date Index ...............                        ║
  504.  ║                                                                             ║
  505.  ║        Preparing the Date/Task Index ................                       ║
  506.  ║                                                                             ║
  507.  ║                                                                             ║
  508.  ║                                                                             ║
  509.  ║                                                                             ║
  510.  ║                                                                             ║
  511.  ╚═════════════════════════════════════════════════════════════════════════════╝
  512.  
  513. Next you get to select all the printing parameters you need to make the
  514. schedule print out just the way you want it.  The screen is pretty well
  515. self explanatory.  Some choices result in messages concerning other
  516. choices in the bottom window.  First the "Date/Task" or "Task/Date"
  517. choice.
  518.  
  519.  
  520.  ╔═════════════════════════════════════════════════════════════════════════════╗
  521.  ║                      ===== Schedule Setup =====                             ║
  522.  ║   Display Sort                                     ---->                    ║
  523.  ║       D = Date/Task          T = Task/Date                                  ║
  524.  ║                                                                             ║
  525.  ║   Enter Project Name ->                                                     ║
  526.  ║                                                                             ║
  527.  ║   Paged or Continuous ?                            ---->                    ║
  528.  ║       P = Paged  C = Continuous                                             ║
  529.  ║   Insert Datelines between Tasks/Names (Y/N)       ---->                    ║
  530.  ║                                                                             ║
  531.  ║   Print Record Control (Y/N)                       ---->                    ║
  532.  ║                                                                             ║
  533.  ║   Print Man-hour/Cost totals (Y/N)                 ---->                    ║
  534.  ║   ========================================================================= ║
  535.  ║                                                                             ║
  536.  ║                                                                             ║
  537.  ║                                                                             ║
  538.  ║                                                                             ║
  539.  ║                                                                             ║
  540.  ║                                                                             ║
  541.  ║                                                                             ║
  542.  ╚═════════════════════════════════════════════════════════════════════════════╝
  543.  
  544.     Next, in the bottom window, you may select <A>ll Tasks or <P>art or a
  545. single task.
  546.  
  547.  
  548.  ╔═════════════════════════════════════════════════════════════════════════════╗
  549.  ║                      ===== Schedule Setup =====                             ║
  550.  ║   Display Sort                                     ----> T                  ║
  551.  ║       D = Date/Task          T = Task/Date                                  ║
  552.  ║                                                                             ║
  553.  ║   Enter Project Name ->                                                     ║
  554.  ║                                                                             ║
  555.  ║   Paged or Continuous ?                            ---->                    ║
  556.  ║       P = Paged  C = Continuous                                             ║
  557.  ║   Insert Datelines between Tasks/Names (Y/N)       ---->                    ║
  558.  ║                                                                             ║
  559.  ║   Print Record Control (Y/N)                       ---->                    ║
  560.  ║                                                                             ║
  561.  ║   Print Man-hour/Cost totals (Y/N)                 ---->                    ║
  562.  ║   ========================================================================= ║
  563.  ║                                                                             ║
  564.  ║                                                                             ║
  565.  ║                                                                             ║
  566.  ║        Reports may be generated for All Tasks <A> -- or --                  ║
  567.  ║        A single task                          <P>                           ║
  568.  ║                  Enter your choice =====>                                   ║
  569.  ║                                                                             ║
  570.  ╚═════════════════════════════════════════════════════════════════════════════╝
  571.  
  572. Next, in the bottom window, we will allow you to filter the Task
  573. Description line for some word or phrase.  If you like you may break a
  574. schedule up into broad phases by making the descriptions look like:
  575.  
  576.     PRE PLAN - Some task
  577.     PRE PLAN - Another
  578.  
  579.     MAIN PHASE - A task
  580.     MAIN PHASE - More
  581.  
  582.     MARKET - A marketing task
  583.     MARKET - and so on ....
  584.  
  585.     Then, if you want the PRE PLAN schedule, filter it for that ....
  586. 'nother neat trick ....
  587.  
  588.     Note: The filter will extract the phrase or word ANYWHERE in the task
  589. description line. ANYWHERE.
  590.  
  591.  ╔═════════════════════════════════════════════════════════════════════════════╗
  592.  ║                      ===== Schedule Setup =====                             ║
  593.  ║   Display Sort                                     ----> T                  ║
  594.  ║       D = Date/Task          T = Task/Date                                  ║
  595.  ║                                                                             ║
  596.  ║   Enter Project Name ->                                                     ║
  597.  ║                                                                             ║
  598.  ║   Paged or Continuous ?                            ---->                    ║
  599.  ║       P = Paged  C = Continuous                                             ║
  600.  ║   Insert Datelines between Tasks/Names (Y/N)       ---->                    ║
  601.  ║                                                                             ║
  602.  ║   Print Record Control (Y/N)                       ---->                    ║
  603.  ║                                                                             ║
  604.  ║   Print Man-hour/Cost totals (Y/N)                 ---->                    ║
  605.  ║   ========================================================================= ║
  606.  ║                                                                             ║
  607.  ║                                                                             ║
  608.  ║                                                                             ║
  609.  ║        We can filter the TASK DESC line for some phrase --                  ║
  610.  ║        or the other. You must enter the phrase EXACTLY as it is             ║
  611.  ║        in the TASK DESC. Upper/lower CASE counts!                           ║
  612.  ║        Enter the PHRASE, <RET> for NO filter  ==>                           ║
  613.  ╚═════════════════════════════════════════════════════════════════════════════╝
  614.  
  615.  
  616.     Next, you get to review what you have selected. If it isn't like you
  617. want, enter <N> and you will get to start over.
  618.  
  619.  
  620.  ╔═════════════════════════════════════════════════════════════════════════════╗
  621.  ║                      ===== Schedule Setup =====                             ║
  622.  ║   Display Sort                                     ----> T                  ║
  623.  ║       D = Date/Task          T = Task/Date                                  ║
  624.  ║                                                                             ║
  625.  ║   Enter Project Name ->                                                     ║
  626.  ║        TEST                                                                 ║
  627.  ║   Paged or Continuous ?                            ----> C                  ║
  628.  ║       P = Paged  C = Continuous                                             ║
  629.  ║   Insert Datelines between Tasks/Names (Y/N)       ----> Y                  ║
  630.  ║                                                                             ║
  631.  ║   Print Record Control (Y/N)                       ----> Y                  ║
  632.  ║                                                                             ║
  633.  ║   Print Man-hour/Cost totals (Y/N)                 ----> Y                  ║
  634.  ║   ========================================================================= ║
  635.  ║                       Your Selected Results                                 ║
  636.  ║ * - Task/Date Sorted                 * - With datelines inserted            ║
  637.  ║ * - With record control numbers      * - With man-hour/cost totals          ║
  638.  ║ * - Continuou≤                                                              ║
  639.  ║                                                                             ║
  640.  ║        If this all looks OK enter <Y>, if not OK enter <N>,                 ║
  641.  ║        -- or -- <*> to bail out --->                                        ║
  642.  ╚═════════════════════════════════════════════════════════════════════════════╝
  643.  
  644.  
  645. Finally, before printing, you get to tell us about your printer.  Note
  646. that if you select the EPSON, and it works for all EPSON command set
  647. printers, you may be able to print in super compressed.  Others can't.
  648.  
  649.  
  650.  ╔═════════════════════════════════════════════════════════════════════════════╗
  651.  ║===> NOTE! B E  S U R E  P A P E R  I S  P R O P E R L Y  S E T !!! <===     ║
  652.  ║                                                                             ║
  653.  ║What type of printer will you be using. Those supported are listed below:    ║
  654.  ║                                                                             ║
  655.  ║                C --> C.Itoh 24LQ                                            ║
  656.  ║                                                                             ║
  657.  ║                H --> Hewlett-Packard Whisper Jet                            ║
  658.  ║                                                                             ║
  659.  ║                T --> Toshiba 1351                                           ║
  660.  ║                                                                             ║
  661.  ║                E --> Epson MX/FX Series 16.5 cpi/8 lines/inch               ║
  662.  ║                                                                             ║
  663.  ║                F --> Epson FX Series 12 cpi / 8 lines/inch                  ║
  664.  ║                                                                             ║
  665.  ║                O --> Okidata u83/93 Series                                  ║
  666.  ║                                                                             ║
  667.  ║                                                                             ║
  668.  ║                * --> Bail out                                               ║
  669.  ║                                                                             ║
  670.  ║        Enter your choice ------>                                            ║
  671.  ║                                                                             ║
  672.  ╚═════════════════════════════════════════════════════════════════════════════╝
  673.  
  674.     The super compressed option looks like:
  675.  
  676. --------------------------------------------------------------------------------
  677.          Schedules may be printed in compressed or super-compressed
  678.          mode --                                                                
  679.          ======> Super compressed only on Epson or Gemini <========             
  680.                                                                                 
  681.                   C -- Compressed mode                                          
  682.                   S -- Super-compressed mode                                    
  683.                                                                                 
  684.                                                                                 
  685.            Enter your choice ----------------------->                           
  686. --------------------------------------------------------------------------------
  687.  
  688.     The message on screen while printing is:
  689.  
  690.  
  691.  
  692.  ╔═════════════════════════════════════════════════════════════════════════════╗
  693.  ║                                                                             ║
  694.  ║   .... Printing the Schedule now ....                                       ║
  695.  ║                                                                             ║
  696.  ╚═════════════════════════════════════════════════════════════════════════════╝
  697.  
  698.  
  699.  
  700.     Next is the printed schedule. Use the -> to move out to the right if
  701. you are looking at this through LIST. If not, you may want to print the
  702. schedule to look at it.
  703.                                                                                                      TEST
  704.  
  705.                                                                                                     03/23/89
  706.  
  707.                 "*" Estimated Dates   "#" Linked Task    "=" Actual Dates       "|" Today      "+" 7 Days from Today
  708.  
  709.  
  710.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  711.  Task Number        Task Name                                         Start     Stop      Len        !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  712.  1.11.001    TASK 1                                                   02/14/89  04/02/89   47        *********************** 04/02 WORK
  713.                ==> Actual Time Spent                                  02/12/89  03/23/89   39       =================== 03/23
  714.                #  1- PERSON -  -  -                                                                                    |   +
  715.                PERSON     -->   300 M/h
  716.                Other Direct Costs  --> $   1350.00
  717.                Man-hour Costs      --> $  15000.00
  718.                Task Costs          --> $  16350.00
  719.  
  720.  1.11.002    NEW TASK                                                 03/22/89  04/26/89   35                          ***************** 04/26     
  721.                #  4- STAFF 1 -  -  -                                                                                   |   +
  722.                STAFF 1    -->    26 M/h
  723.                Other Direct Costs  --> $   3373.00
  724.                Man-hour Costs      --> $   1202.76
  725.                Task Costs          --> $   4575.76
  726.  
  727.  1.11.005    NEW TASK                                                 08/12/89  09/14/89   33                                                                                                 **************** 09/14     
  728.                # 16- PERSON -  -  -                                                                                    |   +
  729.                PERSON     -->    26 M/h
  730.                Other Direct Costs  --> $   4698.00
  731.                Man-hour Costs      --> $   1456.00
  732.                Task Costs          --> $   6154.00
  733.  
  734.      Total Task Man-hours     ===>             352
  735.      Total Task Man-hour cost ===>   $    17658.76
  736.      Total Task ODC           ===>   $     9421.00
  737.      Total Task Cost          ===>   $    27079.76
  738.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  739.                                                                                                      !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  740.  2.11.001    TASK 2                                                   03/17/89  04/30/89   44                       ********************** 04/30 PROB
  741.                #  2- PERSON - PERSON 2 -  -                                                                            |   +
  742.                PERSON     -->   450 M/h
  743.                PERSON 2   -->   230 M/h
  744.                Other Direct Costs  --> $   1750.00
  745.                Man-hour Costs      --> $  34310.00
  746.                Task Costs          --> $  36060.00
  747.  
  748.  2.11.002    LINK TASK 2.11                                           04/30/89  05/23/89   23                                             ########### 05/23     
  749.                # 13- LOGAN -  -  -                                                                                     |   +
  750.                LOGAN      -->    22 M/h
  751.                Man-hour Costs      --> $   1012.00
  752.                Task Costs          --> $   1012.00
  753.  
  754.  2.11.003    ANOTHER ...                                              05/23/89  06/04/89   12                                                         ###### 06/04     
  755.                # 14- LOGAN -  -  -                                                                                     |   +
  756.                LOGAN      -->    16 M/h
  757.                Man-hour Costs      --> $    736.00
  758.                Task Costs          --> $    736.00
  759.  
  760.  2.11.004    ANOTHER ...                                              05/23/89  06/13/89   21                                                         ########## 06/13     
  761.                # 15- LOGAN -  -  -                                                                                     |   +
  762.                LOGAN      -->    66 M/h
  763.                Man-hour Costs      --> $   3036.00
  764.                Task Costs          --> $   3036.00
  765.  
  766.  2.11.005    NEW TASK                                                 06/13/89  07/05/89   22                                                                   ########### 07/05     
  767.                # 17- PERSON -  -  -                                                                                    |   +
  768.                PERSON     -->    45 M/h
  769.                Man-hour Costs      --> $   2520.00
  770.                Task Costs          --> $   2520.00
  771.  
  772.  2.11.006    ANOTHER                                                  06/13/89  07/17/89   34                                                                   ################# 07/17     
  773.                # 18- PERSON -  -  -                                                                                    |   +
  774.                PERSON     -->    34 M/h
  775.                Man-hour Costs      --> $   1904.00
  776.                Task Costs          --> $   1904.00
  777.  
  778.      Total Task Man-hours     ===>             863
  779.      Total Task Man-hour cost ===>   $    43518.00
  780.      Total Task ODC           ===>   $     1750.00
  781.      Total Task Cost          ===>   $    45268.00
  782.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  783.                                                                                                      !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  784.  3.11.001    TASK 3                                                   05/10/89  08/08/89   90                                                  ********************************************* 08/08 WAIT
  785.                #  3- PERSON - PERSON -  -                                                                              |   +
  786.                PERSON     -->   525 M/h
  787.                PERSON     -->   300 M/h
  788.                Other Direct Costs  --> $   5040.36
  789.                Man-hour Costs      --> $  38250.00
  790.                Task Costs          --> $  43290.36
  791.  
  792.      Total Task Man-hours     ===>             825
  793.      Total Task Man-hour cost ===>   $    38250.00
  794.      Total Task ODC           ===>   $     5040.36
  795.      Total Task Cost          ===>   $    43290.36
  796.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  797.                                                                                                      !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  798.  4.11.001    WHALES, SNAILS, & PUPPY DOG TAILS                        06/12/89  08/23/89   72                                                                   ************************************ 08/23     
  799.                #  5- CORLIN - ATWELL -  -                                                                              |   +
  800.                CORLIN     -->    46 M/h
  801.                ATWELL     -->    23 M/h
  802.                Other Direct Costs  --> $   2948.00
  803.                Man-hour Costs      --> $   3671.95
  804.                Task Costs          --> $   6619.95
  805.  
  806.      Total Task Man-hours     ===>              69
  807.      Total Task Man-hour cost ===>   $     3671.95
  808.      Total Task ODC           ===>   $     2948.00
  809.      Total Task Cost          ===>   $     6619.95
  810.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  811.                                                                                                      !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  812.  5.11.001    FIRST                                                    07/01/89  07/13/89   12                                                                            ###### 07/13     
  813.                #  6- NAME -  -  -                                                                                      |   +
  814.                NAME       -->    22 M/h
  815.                Man-hour Costs      --> $    726.00
  816.                Task Costs          --> $    726.00
  817.  
  818.  5.11.002    SECOND                                                   07/13/89  07/23/89   10                                                                                  ##### 07/23     
  819.                #  7- NAME -  -  -                                                                                      |   +
  820.                NAME       -->    44 M/h
  821.                Man-hour Costs      --> $   2420.00
  822.                Task Costs          --> $   2420.00
  823.  
  824.  5.11.003    THIRD                                                    07/13/89  07/26/89   13                                                                                  ###### 07/26     
  825.                #  8- NAME -  -  -                                                                                      |   +
  826.                NAME       -->    66 M/h
  827.                Man-hour Costs      --> $   1452.00
  828.                Task Costs          --> $   1452.00
  829.  
  830.  5.11.004    FOURTH                                                   07/13/89  07/30/89   17                                                                                  ######## 07/30     
  831.                #  9- NAME -  -  -                                                                                      |   +
  832.                NAME       -->    44 M/h
  833.                Man-hour Costs      --> $   2420.00
  834.                Task Costs          --> $   2420.00
  835.  
  836.  5.11.005    FIFTH                                                    07/13/89  08/01/89   19                                                                                  ######### 08/01     
  837.                # 10- NAME -  -  -                                                                                      |   +
  838.                NAME       -->    44 M/h
  839.                Man-hour Costs      --> $   2420.00
  840.                Task Costs          --> $   2420.00
  841.  
  842.  5.11.006    SIXTH                                                    08/01/89  08/23/89   22                                                                                            ########### 08/23     
  843.                # 11- NAME -  -  -                                                                                      |   +
  844.                NAME       -->    44 M/h
  845.                Man-hour Costs      --> $   2420.00
  846.                Task Costs          --> $   2420.00
  847.  
  848.  5.11.007    SEVENTH                                                  09/04/89  09/16/89   12                                                                                                             ###### 09/16     
  849.                # 12- NAME -  -  -                                                                                      |   +
  850.                NAME       -->    12 M/h
  851.                Man-hour Costs      --> $    408.00
  852.                Task Costs          --> $    408.00
  853.  
  854.      Total Task Man-hours     ===>             276
  855.      Total Task Man-hour cost ===>   $    12266.00
  856.      Total Task ODC           ===>   $        0.00
  857.      Total Task Cost          ===>   $    12266.00
  858.  
  859.                                                                                                      !----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!----!
  860.                                                                                                    02/14     03/06     03/26     04/15     05/05     05/25     06/14     07/04     07/24     08/13     09/02     09/22     10/12     
  861.  
  862.           PROJECT LENGTH IS   214 DAY(s) 
  863.  
  864.           NOTE "|" If present, is today's date.  03/23/89  "+" If present, is seven days from today
  865.  
  866.           EACH SYMBOL REPRESENTS  2 DAY(s)
  867.  
  868.           TOTAL  ESTIMATED MAN-HOURS          =====>          2385 M/H
  869.  
  870.           TOTAL ESTIMATED MAN-HOUR COSTS      =====> $   115364.71
  871.  
  872.           TOTAL PROJECTED OTHER DIRECT COSTS  =====> $    19159.36
  873.  
  874.           TOTAL PROJECTED COST                =====> $   134524.07
  875.  
  876.  
  877.     At the conclusion of printing, you are returned to the Main Menu
  878.  
  879. G. Print Direct Cost Breakdown Report.
  880.  
  881.     First you need to Title the report:
  882.  
  883. -------------------------------------------------------------------------------
  884.  
  885. Enter the desired report header ----> DC for test_2                             
  886.                                                                                 
  887. -------------------------------------------------------------------------------
  888.  
  889.     Then printer selection:
  890.  
  891.  
  892.  ╔═════════════════════════════════════════════════════════════════════════════╗
  893.  ║===> NOTE! B E  S U R E  P A P E R  I S  P R O P E R L Y  S E T !!! <===     ║
  894.  ║                                                                             ║
  895.  ║What type of printer will you be using. Those supported are listed below:    ║
  896.  ║                                                                             ║
  897.  ║                C --> C.Itoh 24LQ                                            ║
  898.  ║                                                                             ║
  899.  ║                H --> Hewlett-Packard Whisper Jet                            ║
  900.  ║                                                                             ║
  901.  ║                T --> Toshiba 1351                                           ║
  902.  ║                                                                             ║
  903.  ║                E --> Epson MX/FX Series 16.5 cpi/8 lines/inch               ║
  904.  ║                                                                             ║
  905.  ║                F --> Epson FX Series 12 cpi / 8 lines/inch                  ║
  906.  ║                                                                             ║
  907.  ║                O --> Okidata u83/93 Series                                  ║
  908.  ║                                                                             ║
  909.  ║                                                                             ║
  910.  ║                * --> Bail out                                               ║
  911.  ║                                                                             ║
  912.  ║        Enter your choice ------>                                            ║
  913.  ║                                                                             ║
  914.  ╚═════════════════════════════════════════════════════════════════════════════╝
  915.  
  916. Then the report itself.  Note that the report is totaled two directions
  917. so that you can see the cost of any task horizontally and the cost of
  918. travel vertically.
  919.  
  920.  
  921.         Page No.     1                                                                                           DC for test_2
  922.         03/23/89
  923.                                                                                                           DIRECT COST BREAKDOWN REPORT
  924.         
  925.         Task NO.     Task Desc.                    Start      Stop         Est M/H    M/H Cost      Travel        Food     Lodging        Auto       Equip      Copies       Admin     Support        Misc   ODC Total
  926.         
  927.         
  928.         1.11.001     TASK 1                        02/14/89   04/02/89         300    15000.00      450.00      450.00      450.00        0.00        0.00        0.00        0.00        0.00        0.00     1350.00
  929.         1.11.002     NEW TASK                      03/22/89   04/26/89          26     1202.76     2350.00      345.00      678.00        0.00        0.00        0.00        0.00        0.00        0.00     3373.00
  930.         1.11.005     NEW TASK                      08/12/89   09/14/89          26     1456.00     2300.00      677.00      997.00      285.00       46.00       25.00       18.00      150.00      200.00     4698.00
  931.         2.11.001     TASK 2                        03/17/89   04/30/89         680    34310.00      250.00      350.00      450.00        0.00        0.00        0.00        0.00      250.00      450.00     1750.00
  932.         2.11.002     LINK TASK 2.11                04/30/89   05/23/89          22     1012.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  933.         2.11.003     ANOTHER ...                   05/23/89   06/04/89          16      736.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  934.         2.11.004     ANOTHER ...                   05/23/89   06/13/89          66     3036.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  935.         2.11.005     NEW TASK                      06/13/89   07/05/89          45     2520.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  936.         2.11.006     ANOTHER                       06/13/89   07/17/89          34     1904.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  937.         3.11.001     TASK 3                        05/10/89   08/08/89         825    38250.00     2350.00      866.00      921.36      255.00       48.00       50.00      450.00      100.00        0.00     5040.36
  938.         4.11.001     WHALES, SNAILS, & PUPPY       06/12/89   08/23/89          69     3671.95     1200.00      450.00      976.00      125.00       47.00        0.00        0.00        0.00      150.00     2948.00
  939.                      DOG TAILS                                                                                                                                                                                        
  940.         5.11.001     FIRST                         07/01/89   07/13/89          22      726.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  941.         5.11.002     SECOND                        07/13/89   07/23/89          44     2420.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  942.         5.11.003     THIRD                         07/13/89   07/26/89          66     1452.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  943.         5.11.004     FOURTH                        07/13/89   07/30/89          44     2420.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  944.         5.11.005     FIFTH                         07/13/89   08/01/89          44     2420.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  945.         5.11.006     SIXTH                         08/01/89   08/23/89          44     2420.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  946.         5.11.007     SEVENTH                       09/04/89   09/16/89          12      408.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00        0.00
  947.         *** Total ***
  948.                                                                               2385   115364.71     8900.00     3138.00     4472.36      665.00      141.00       75.00      468.00      500.00      800.00    19159.36
  949.  
  950.  
  951. D. Enter Actual Dates
  952.  
  953. Actual dates may be entered or edited from this selection.  Actual dates
  954. appear both on the printed schedule and on the screen list.  On the
  955. printed schedule they appear as "=" lines.  If you enter an actual start
  956. date and no stop date and the status comment for that task is NOT "COMP"
  957. the program will automatically insert the current date for the task as
  958. its "stop" date, thus it will automatically precess your chart.  You can
  959. stop the task by entering "COMP" as a Status Comment.
  960.  
  961.  
  962.  ╔═════════════════════════════════════════════════════════════════════════════╗
  963.  ║                                                                             ║
  964.  ║                                                                             ║
  965.  ║                  Control Number ====>     4                                 ║
  966.  ║                                                                             ║
  967.  ║                                                                             ║
  968.  ║                                                                             ║
  969.  ║                  Task Number    ====>  1.11       Sub Task ====>  002       ║
  970.  ║                                                                             ║
  971.  ║   Task Description ==>  NEW TASK                                            ║
  972.  ║=============================================================================║
  973.  ║        Proposed Start Date           Proposed Stop Date                     ║
  974.  ║         03/22/89                      04/26/89                              ║
  975.  ║                                                                             ║
  976.  ║        Actual Start Date             Actual Stop Date                       ║
  977.  ║         03/23/89                        /  /                                ║
  978.  ║=============================================================================║
  979.  ║                                                                             ║
  980.  ║                                                                             ║
  981.  ║                                                                             ║
  982.  ║                                                                             ║
  983.  ║                                                                             ║
  984.  ╚═════════════════════════════════════════════════════════════════════════════╝
  985.  
  986.     When you finish the first record you can go on, if you like:
  987.  
  988. -------------------------------------------------------------------------------
  989.  
  990.                     Do Another ?  (Y/N)  ----->
  991.                                                                                 
  992. -------------------------------------------------------------------------------
  993.                                                                                 
  994. I.  Inflate/deflate M/H.  If you need to expand or contract the man
  995. hours on the whole schedule or just one task, this is the way to do
  996. that.  Note that the default is 1.00, so if you press <ENTER>, nothing
  997. will really happen.  Actually all man-hours will be multiplied by 1.00
  998.  
  999.  
  1000.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1001.  ║                   INFLATE  or  DEFLATE  MAN-HOURS                           ║
  1002.  ║                                                                             ║
  1003.  ║  This little sweetie will allow you to inflate or deflate the               ║
  1004.  ║  man-hours for all the tasks in a given schedule. To inflate,               ║
  1005.  ║  use a factor greater than 1 and to deflate, use a factor less than 1.      ║
  1006.  ║  I don't recommend use negative factors, but if you are adventurous,        ║
  1007.  ║  why, give it a try ...                                                     ║
  1008.  ║                                                                             ║
  1009.  ║        Enter the inflation/deflation factor ===>            1.00            ║
  1010.  ║                                                                             ║
  1011.  ║        All tasks <ENTER> -- or -- a specific task --->                      ║
  1012.  ║                                                                             ║
  1013.  ║                                                                             ║
  1014.  ║                                                                             ║
  1015.  ║                                                                             ║
  1016.  ║                                                                             ║
  1017.  ║                                                                             ║
  1018.  ║                                                                             ║
  1019.  ║                                                                             ║
  1020.  ║                                                                             ║
  1021.  ║                                                                             ║
  1022.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1023.  
  1024.  
  1025.  
  1026.  
  1027. T. Date Tricks
  1028.  
  1029.     Date tricks allows you to move your schedule backwards and forwards
  1030. in time. The screens look like:
  1031.  
  1032.                                                                                 
  1033.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1034.  ║             ----------   DATE TRICKS  -----------                           ║
  1035.  ║                                                                             ║
  1036.  ║  From this menu you may 'mess around' with the proposed dates               ║
  1037.  ║  in your schedule. Two things can be done. Either can be for all tasks      ║
  1038.  ║  or a specific Task Number.                                                 ║
  1039.  ║                                                                             ║
  1040.  ║      A   --  Slide all dates (ahead or back) a certain amount               ║
  1041.  ║                                                                             ║
  1042.  ║      B   --  Expand spans of jobs by a percent (greater than 1              ║
  1043.  ║              expands while less than one contracts -- start                 ║
  1044.  ║              dates are left alone)                                          ║
  1045.  ║                                                                             ║
  1046.  ║      *   --  Return to Main Menu                                            ║
  1047.  ║                                                                             ║
  1048.  ║        Enter your choice ===>                                               ║
  1049.  ║                                                                             ║
  1050.  ║                                                                             ║
  1051.  ║                                                                             ║
  1052.  ║                                                                             ║
  1053.  ║                                                                             ║
  1054.  ║                                                                             ║
  1055.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1056.                                                                                 
  1057.                                                                                 
  1058.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1059.  ║             ----------   DATE TRICKS  -----------                           ║
  1060.  ║                                                                             ║
  1061.  ║  From this menu you may 'mess around' with the proposed dates               ║
  1062.  ║  in your schedule. Two things can be done. Either can be for all tasks      ║
  1063.  ║  or a specific Task Number.                                                 ║
  1064.  ║                                                                             ║
  1065.  ║      A   --  Slide all dates (ahead or back) a certain amount               ║
  1066.  ║                                                                             ║
  1067.  ║      B   --  Expand spans of jobs by a percent (greater than 1              ║
  1068.  ║              expands while less than one contracts -- start                 ║
  1069.  ║              dates are left alone)                                          ║
  1070.  ║                                                                             ║
  1071.  ║      *   --  Return to Main Menu                                            ║
  1072.  ║                                                                             ║
  1073.  ║        Enter your choice ===>   A                                           ║
  1074.  ║                                                                             ║
  1075.  ║        Do it to A)ctual and Planned -- or -- P)lanned ONLY --->             ║
  1076.  ║                                                                             ║
  1077.  ║                                                                             ║
  1078.  ║                                                                             ║
  1079.  ║                                                                             ║
  1080.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1081.                                                                                 
  1082.                                                                                 
  1083.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1084.  ║             ----------   DATE TRICKS  -----------                           ║
  1085.  ║                                                                             ║
  1086.  ║  From this menu you may 'mess around' with the proposed dates               ║
  1087.  ║  in your schedule. Two things can be done. Either can be for all tasks      ║
  1088.  ║  or a specific Task Number.                                                 ║
  1089.  ║                                                                             ║
  1090.  ║      A   --  Slide all dates (ahead or back) a certain amount               ║
  1091.  ║                                                                             ║
  1092.  ║      B   --  Expand spans of jobs by a percent (greater than 1              ║
  1093.  ║              expands while less than one contracts -- start                 ║
  1094.  ║              dates are left alone)                                          ║
  1095.  ║                                                                             ║
  1096.  ║      *   --  Return to Main Menu                                            ║
  1097.  ║                                                                             ║
  1098.  ║        Enter your choice ===>   A                                           ║
  1099.  ║                                                                             ║
  1100.  ║        Do it to A)ctual and Planned -- or -- P)lanned ONLY --->   A         ║
  1101.  ║                                                                             ║
  1102.  ║        Enter the number of days (+ or -) --->            0                  ║
  1103.  ║                                                                             ║
  1104.  ║        All tasks <ENTER> -- or -- a specific Task No. --->                  ║
  1105.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1106.                                                                                 
  1107.                                                                                 
  1108.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1109.  ║             ----------   DATE TRICKS  -----------                           ║
  1110.  ║                                                                             ║
  1111.  ║  From this menu you may 'mess around' with the proposed dates               ║
  1112.  ║  in your schedule. Two things can be done. Either can be for all tasks      ║
  1113.  ║  or a specific Task Number.                                                 ║
  1114.  ║                                                                             ║
  1115.  ║      A   --  Slide all dates (ahead or back) a certain amount               ║
  1116.  ║                                                                             ║
  1117.  ║      B   --  Expand spans of jobs by a percent (greater than 1              ║
  1118.  ║              expands while less than one contracts -- start                 ║
  1119.  ║              dates are left alone)                                          ║
  1120.  ║                                                                             ║
  1121.  ║      *   --  Return to Main Menu                                            ║
  1122.  ║                                                                             ║
  1123.  ║        Enter your choice ===>   B                                           ║
  1124.  ║                                                                             ║
  1125.  ║        Do it to A)ctual and Planned -- or -- P)lanned ONLY --->   A         ║
  1126.  ║                                                                             ║
  1127.  ║        Enter the expansion/contraction factor --->            1.00          ║
  1128.  ║                                                                             ║
  1129.  ║        All tasks <ENTER> -- or -- a specific Task No. --->                  ║
  1130.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1131.  
  1132.  
  1133. R. Hourly Rate Tricks
  1134.  
  1135. Hourly rate tricks allows you to expand or contract the hourly rates
  1136. either for the whole schedule or for a single task inside the schedule.
  1137. The screens look like:
  1138.  
  1139.                                                                                 
  1140.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1141.  ║                                                                             ║
  1142.  ║  From this menu you may 'mess around' with the proposed hourly rates        ║
  1143.  ║  in your schedule. Two things can be done.                                  ║
  1144.  ║                                                                             ║
  1145.  ║      A   --  Expand or contract all hourly rates. Factors greater           ║
  1146.  ║              than one expand and those less than one contract.              ║
  1147.  ║                                                                             ║
  1148.  ║      *   --  Return to Main Menu                                            ║
  1149.  ║                                                                             ║
  1150.  ║                                                                             ║
  1151.  ║                                                                             ║
  1152.  ║                                                                             ║
  1153.  ║        Enter your choice ===>                                               ║
  1154.  ║                                                                             ║
  1155.  ║                                                                             ║
  1156.  ║                                                                             ║
  1157.  ║                                                                             ║
  1158.  ║                                                                             ║
  1159.  ║                                                                             ║
  1160.  ║                                                                             ║
  1161.  ║                                                                             ║
  1162.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1163.                                                                                 
  1164.                                                                                 
  1165.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1166.  ║                                                                             ║
  1167.  ║  From this menu you may 'mess around' with the proposed hourly rates        ║
  1168.  ║  in your schedule. Two things can be done.                                  ║
  1169.  ║                                                                             ║
  1170.  ║      A   --  Expand or contract all hourly rates. Factors greater           ║
  1171.  ║              than one expand and those less than one contract.              ║
  1172.  ║                                                                             ║
  1173.  ║      *   --  Return to Main Menu                                            ║
  1174.  ║                                                                             ║
  1175.  ║                                                                             ║
  1176.  ║                                                                             ║
  1177.  ║                                                                             ║
  1178.  ║        Enter your choice ===>   A                                           ║
  1179.  ║                                                                             ║
  1180.  ║        Enter the expansion/contraction factor --->            1.00          ║
  1181.  ║                                                                             ║
  1182.  ║        All tasks <ENTER> -- or -- a specific task --->                      ║
  1183.  ║                                                                             ║
  1184.  ║                                                                             ║
  1185.  ║                                                                             ║
  1186.  ║                                                                             ║
  1187.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1188.  
  1189.  
  1190. Q. ODC Rate Tricks
  1191.  
  1192. ODC tricks allows you to expand or contract the ODCs by schedule or by
  1193. single task.  It looks like:
  1194.                                                                                 
  1195.                                                                                 
  1196.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1197.  ║                                                                             ║
  1198.  ║  From this menu you may 'mess around' with the proposed Other Direct        ║
  1199.  ║  Costs (ODC) in your schedule. Two things can be done.                      ║
  1200.  ║                                                                             ║
  1201.  ║      A   --  Expand or contract all ODCs. Factors greater                   ║
  1202.  ║              than one expand and those less than one contract.              ║
  1203.  ║                                                                             ║
  1204.  ║      *   --  Return to Main Menu                                            ║
  1205.  ║                                                                             ║
  1206.  ║                                                                             ║
  1207.  ║                                                                             ║
  1208.  ║                                                                             ║
  1209.  ║        Enter your choice ===>   A                                           ║
  1210.  ║                                                                             ║
  1211.  ║        Enter the expansion/contraction factor --->            1.00          ║
  1212.  ║                                                                             ║
  1213.  ║        All tasks <ENTER> -- or -- a specific task --->                      ║
  1214.  ║                                                                             ║
  1215.  ║                                                                             ║
  1216.  ║                                                                             ║
  1217.  ║                                                                             ║
  1218.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1219.  
  1220.  
  1221.  
  1222. F. Delete a Task. This deletion program works on SINGLE records. The
  1223. safest way, I think.
  1224.  
  1225.  
  1226.  
  1227. -------------------------------------------------------------------------------
  1228.  
  1229.  
  1230.           Enter the control number to delete ---->   3                          
  1231.                                                                                 
  1232.                                                                                 
  1233. -------------------------------------------------------------------------------
  1234.  
  1235.     The record is called forth so you can be sure its really the one you
  1236. want to ZAP and you can say either <Y> or <N> to deleting it. Note that
  1237. you need to re-do SETUP when next called for since SETUP seeks out
  1238. earliest and latest dates and this one might have been one or the other.
  1239.  
  1240.  
  1241.  
  1242.           03/23/89          Schedule Item Killer            Control # ===>    3 
  1243. +------------------------------------------------------------------------------+
  1244. |    Task Description ---> TASK 3                                              |
  1245. +------------------------------------------------------------------------------+
  1246. |    Task Number      ---> 3.11                                                |
  1247. +------------------------------------------------------------------------------+
  1248. |    Name             ---> PERSON - PERSON -  -                                |
  1249. +------------------------------------------------------------------------------+
  1250. |    Status           ---> WAIT                                                |
  1251. +------------------------------------------------------------------------------+
  1252. |    Proposed Start   ---> 05/10/89     Proposed Stop    ---> 08/08/89         |
  1253. +------------------------------------------------------------------------------+
  1254. |    Actual Start     --->   /  /       Actual Stop      --->   /  /           |
  1255. +------------------------------------------------------------------------------+
  1256. |              Estimated Man Hours     --->   825                              |
  1257. +------------------------------------------------------------------------------+
  1258. |              Estimated Cost          --->   5040.36                          |
  1259. +------------------------------------------------------------------------------+
  1260. |                                                                              |
  1261. |                                                                              |
  1262. |                                                                              |
  1263. |                        Delete this task ? (Y/N)  ----->                      |
  1264. +------------------------------------------------------------------------------+
  1265.  
  1266.     When one is complete, you can do more
  1267.  
  1268.  
  1269. -------------------------------------------------------------------------------
  1270.  
  1271.           Do another ? (Y/N) ---->                                              
  1272.                                                                                 
  1273. -------------------------------------------------------------------------------
  1274.                                                                                 
  1275.     <N> will return you to the Main Menu.
  1276.                                                                                 
  1277. L. List Schedule to Screen. First, how would you like the display sorted?
  1278.                                                                                 
  1279.                                                                                 
  1280. -------------------------------------------------------------------------------
  1281.                                                                                 
  1282.           How would you like the display sorted?                                
  1283.                                                                                 
  1284.              A   --  Task/Date                                                  
  1285.              B   --  Date/Task                                                  
  1286.                                                                                 
  1287.           Enter your choice --->                                                
  1288.                                                                                 
  1289. -------------------------------------------------------------------------------
  1290.                                                                                 
  1291.     Then a chance to do SETUP, if you want to.
  1292.                                                                                 
  1293. -------------------------------------------------------------------------------
  1294.                                                                                 
  1295.           If you know that the setup procedures are correct, you may            
  1296.           skip the SETUP program                                                
  1297.           S will skip SETUP procedures -- or --                                 
  1298.           D or <CR> will execute SETUP ---->                                    
  1299.                                                                                 
  1300. -------------------------------------------------------------------------------
  1301.                                                                                 
  1302.     The screen display follows. Prt Sc will send this to your printer, if
  1303. you'd like a printed copy.
  1304.                                                                                 
  1305. -------------------------------------------------------------------------------
  1306.  Task No.      Description                Start    Stop     Hrs  Span  Cntr No. 
  1307.  ------------+---------------------------+--------+--------+-----+----+-------- 
  1308.  1.11.001     TASK 1                      02/14/89 04/02/89   300   47     1    
  1309.               Actual -->                  02/12/89 03/23/89 WORK                
  1310.  1.11.002     NEW TASK                    03/22/89 04/26/89    26   35     4    
  1311.               Actual -->                  03/23/89 03/23/89 WORK                
  1312.  1.11.005     NEW TASK                    08/12/89 09/14/89    26   33    16    
  1313.  2.11.001     TASK 2                      03/17/89 04/30/89   680   44     2    
  1314.  2.11.002     LINK TASK 2.11              04/30/89 05/23/89    22   23    13    
  1315.  2.11.003     ANOTHER ...                 05/23/89 06/04/89    16   12    14    
  1316.  2.11.004     ANOTHER ...                 05/23/89 06/13/89    66   21    15    
  1317.  2.11.005     NEW TASK                    06/13/89 07/05/89    45   22    17    
  1318.  2.11.006     ANOTHER                     06/13/89 07/17/89    34   34    18    
  1319.  3.11.001     TASK 3                      05/10/89 08/08/89   825   90     3    
  1320.  4.11.001     WHALES, SNAILS, & PUPPY D   06/12/89 08/23/89    69   72     5    
  1321.  5.11.001     FIRST                       07/01/89 07/13/89    22   12     6    
  1322.  5.11.002     SECOND                      07/13/89 07/23/89    44   10     7    
  1323.  5.11.003     THIRD                       07/13/89 07/26/89    66   13     8
  1324.  5.11.004     FOURTH                      07/13/89 07/30/89    44   17     9    
  1325.                                                                                 
  1326.                                                                                 
  1327.                                                                                 
  1328.                Press <RET> to continue ... or <*> to quit ...                   
  1329. -------------------------------------------------------------------------------
  1330.  
  1331.     The second page
  1332.  
  1333. -------------------------------------------------------------------------------
  1334.  Task No.      Description                Start    Stop     Hrs  Span  Cntr No. 
  1335.  ------------+---------------------------+--------+--------+-----+----+-------- 
  1336.  5.11.005     FIFTH                       07/13/89 08/01/89    44   19    10    
  1337.  5.11.006     SIXTH                       08/01/89 08/23/89    44   22    11    
  1338.  5.11.007     SEVENTH                     09/04/89 09/16/89    12   12    12    
  1339.                                                                                 
  1340.                                                                                 
  1341.                     Total Estimated Man/hours ===>           2385  214          
  1342.                                                                                 
  1343.                                                                                 
  1344.                                                                                 
  1345.                                                                                 
  1346.                                                                                 
  1347.                                                                                 
  1348.                                                                                 
  1349.                Press <RET> to continue ...                                      
  1350. -------------------------------------------------------------------------------
  1351.  
  1352. U.  System Utilities.  The SCHEDULE system is set up for a hard disk
  1353. called C:.  If yours is different, you can get space from <D>.  Valid
  1354. drives go from A to I, since it may get on a network somewhere.  I have
  1355. noticed on one network that the sizes aren't right.  I expect it's
  1356. because of the way size is done on the network op system.  The amount of
  1357. memory available is in "K" and is here in case your program that you
  1358. want to run, won't. Probably not enough memory.  Running a program is
  1359. straight-forward.  Enter the name and any arguments and press enter.  It
  1360. either runs or not.  The printer re-direct <S> is useful for getting
  1361. results in files rather than on paper.  Before the file can be used, it
  1362. must be closed <P>.  If LIST is in your path, and it should be, then you
  1363. can look at the file, JUNK.XXX. renaming of a (closed) JUNK.XXX can be
  1364. done as a <R> as REN JUNK.XXX TRASH.YYY.  ESC is the ONLY way out of the
  1365. UTILITY menu.  Some example screens follow:
  1366.  
  1367.  
  1368.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1369.  ║                        ====== S C H E D U L E ======                        ║
  1370.  ║                       ======= System Utilities ========                     ║
  1371.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1372.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1373.  ║                                                                             ║
  1374.  ║                  Memory Available =    39                                   ║
  1375.  ║                  Disk space on C: =   1638400                               ║
  1376.  ║                                                                             ║
  1377.  ║                                                                             ║
  1378.  ║                                                                             ║
  1379.  ║                                                                             ║
  1380.  ║                                                                             ║
  1381.  ║                                                                             ║
  1382.  ║                  D   --  Disk space on Other drives                         ║
  1383.  ║                  R   --  Run a Program from Inside SCHEDULE                 ║
  1384.  ║                  S   --  Set Up Printer Re-direct                           ║
  1385.  ║                  P   --  Close Printer Re-direct                            ║
  1386.  ║                  V   --  View Contents of JUNK.XXX                          ║
  1387.  ║                  ESC --  Return to Main Menu                                ║
  1388.  ║                                                                             ║
  1389.  ║                                                                             ║
  1390.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1391.                                                                                 
  1392.                                                                                 
  1393.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1394.  ║                        ====== S C H E D U L E ======                        ║
  1395.  ║                       ======= System Utilities ========                     ║
  1396.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1397.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1398.  ║                                                                             ║
  1399.  ║                  Memory Available =    39                                   ║
  1400.  ║                  Disk space on C: =   1638400                               ║
  1401.  ║                  Enter DRIVE LETTER ===>   A                                ║
  1402.  ║                  Disk space on A: =     58368                               ║
  1403.  ║                                                                             ║
  1404.  ║                                                                             ║
  1405.  ║                                                                             ║
  1406.  ║                                                                             ║
  1407.  ║                  D   --  Disk space on Other drives                         ║
  1408.  ║                  R   --  Run a Program from Inside SCHEDULE                 ║
  1409.  ║                  S   --  Set Up Printer Re-direct                           ║
  1410.  ║                  P   --  Close Printer Re-direct                            ║
  1411.  ║                  V   --  View Contents of JUNK.XXX                          ║
  1412.  ║                  ESC --  Return to Main Menu                                ║
  1413.  ║                                                                             ║
  1414.  ║                                                                             ║
  1415.  ╚════════....... Press <ENTER> to continue ........═══════════════════════════╝
  1416.                                                                                 
  1417.                                                                                 
  1418.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1419.  ║                        ====== S C H E D U L E ======                        ║
  1420.  ║                       ======= System Utilities ========                     ║
  1421.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1422.  ╔═════════════════════════════════════════════════════════════════════════════╗
  1423.  ║                                                                             ║
  1424.  ║                  Memory Available =    39                                   ║
  1425.  ║                  Disk space on C: =   1638400                               ║
  1426.  ║                  Enter the program name (with arguments) to run             ║
  1427.  ║                  ===>   D A:                                                ║
  1428.  ║                                                                             ║
  1429.  ║                                                                             ║
  1430.  ║                                                                             ║
  1431.  ║                                                                             ║
  1432.  ║                  D   --  Disk space on Other drives                         ║
  1433.  ║                  R   --  Run a Program from Inside SCHEDULE                 ║
  1434.  ║                  S   --  Set Up Printer Re-direct                           ║
  1435.  ║                  P   --  Close Printer Re-direct                            ║
  1436.  ║                  V   --  View Contents of JUNK.XXX                          ║
  1437.  ║                  ESC --  Return to Main Menu                                ║
  1438.  ║                                                                             ║
  1439.  ║                                                                             ║
  1440.  ╚═════════════════════════════════════════════════════════════════════════════╝
  1441.                                                                                 
  1442. K.  Create a New Schedule.  Finally, new schedules are created from <K>.
  1443. You can enter an existing name and wipe out a schedule.  I have tried to
  1444. make it hard to do that, but you may want to trash what's in a file for
  1445. new stuff.  A newly created schedule is put in "USE" immediately and you
  1446. may proceed to add <A> or <Z>, which ever you fancy.
  1447.  
  1448. -------------------------------------------------------------------------------
  1449. Database Files    # Records    Last Update     Size                             
  1450. TEST_2.DBF               18    03/23/89       11710                             
  1451. CM.DBF                   32    03/23/89       19522                             
  1452. SKED.DBF                  0    03/23/89        1666                             
  1453. TEST_1.DBF               13    03/23/89        8920                             
  1454.                                                                                 
  1455.                                                                                 
  1456.                                                                                 
  1457.                                                                                 
  1458.                                                                                 
  1459.                                                                                 
  1460.                                                                                 
  1461.                                                                                 
  1462.                                                                                 
  1463.                                                                                 
  1464.                                                                                 
  1465.           Use one of the ABOVE names ONLY IF you want to start over!            
  1466.           Enter the schedule name ---->                                         
  1467.                                                                                 
  1468. -------------------------------------------------------------------------------
  1469.                                                                                 
  1470.     Picking, say TEST_3, the screen looks like:
  1471.  
  1472. -------------------------------------------------------------------------------
  1473. Database Files    # Records    Last Update     Size                             
  1474. TEST_2.DBF               18    03/23/89       11710                             
  1475. CM.DBF                   32    03/23/89       19522                             
  1476. SKED.DBF                  0    03/23/89        1666                             
  1477. TEST_1.DBF               13    03/23/89        8920                             
  1478.                                                                                 
  1479.                                                                                 
  1480.                                                                                 
  1481.                                                                                 
  1482.                                                                                 
  1483.                                                                                 
  1484.                                                                                 
  1485.                                                                                 
  1486.                                                                                 
  1487.                                                                                 
  1488.                                                                                 
  1489.                                                                                 
  1490.                                                                                 
  1491.                                                                                 
  1492.           Use one of the ABOVE names ONLY IF you want to start over!            
  1493.           Enter the schedule name ---->   TEST_3
  1494. -------------------------------------------------------------------------------
  1495.                                                                                 
  1496.     Note that the Main Menu shows TEST_3 in "USE"
  1497.                                                                                 
  1498. ╔══════════════════════════════════════════════════════════════════════════════╗
  1499. ║ July 929                     GANTT CHART SCHEDULER               Ver 4.33    ║
  1500. ║                                by William H. Logan                           ║
  1501. ╚══════════════════════════════════════════════════════════════════════════════╝
  1502. ╔═══════════════════════════════════════╗╔═════════════════════════════════════╗
  1503. ║ A   -- Add tasks to a NEW or          ║║  I   -- Inflate/deflate M/H         ║
  1504. ║        EXISTING Schedule (DATE TYPE)  ║║  T   -- Date Tricks                 ║
  1505. ║ Z   -- Add tasks, NEW or OLD          ║║  R   -- Hourly Rate Tricks          ║
  1506. ║        (LINK TYPE)                    ║║  Q   -- ODC Rate Tricks             ║
  1507. ║ B   -- EDIT an Existing Schedule      ║║                                     ║
  1508. ║                                       ║║  F   -- DELETE a Task in a Project  ║
  1509. ║ C   -- PRINT a Schedule               ║║                                     ║
  1510. ║ G   -- PRINT Direct Cost Breakdown    ║║  L   -- List Schedule to Screen     ║
  1511. ║        Report                         ║║                                     ║
  1512. ║                                       ║║  U   -- System Utilities            ║
  1513. ║ D   -- Enter Actual Dates             ║║  K   -- Create New Schedule         ║
  1514. ║ E   -- Enter Status Comments          ║║  S   -- Select Schedule             ║
  1515. ║                                       ║║                                     ║
  1516. ║ *   -- Quit to Operating System       ║║  Schedule ==>  TEST_3               ║
  1517. ╚═══════════════════════════════════════╝╚═════════════════════════════════════╝
  1518. ╔══════════════════════════════════════════════════════════════════════════════╗
  1519. ║         Enter your choice --->                                               ║
  1520. ╚══════════════════════════════════════════════════════════════════════════════╝
  1521.                                                                                 
  1522. I hope this system will be of as much help to you as it has been to me.
  1523. I have knocked out project estimates in all parts of the world with this
  1524. and have managed large programming projects with it.
  1525.  
  1526. If you need help or get in real trouble I can be reached at
  1527.  
  1528.         William H. Logan
  1529.         408-649-4500
  1530.         408-384-3631 eves & weekends.
  1531.  
  1532.         Send Contributions to :
  1533.                 
  1534.                 2400 Garden Road
  1535.                 Monterey, CA 93940
  1536.  
  1537.         
  1538.  